Project initiation Jan 07, 2013
Survey completion February 08, 2013
Requirements elicitation February 21, 2013
Develop demonstration script March 22, 2013
RFI developmment and placement on BC Bid February 25, 2013
RFI results March 28, 2013
Deliver software vendor demonstrations April 09, 2013
Write RFP May 09, 2013
Select Vendor June 07, 2013
Sign contract June 21, 2013
Configure Contact Centre Solution July 5, 2013
Training: Agents, supervisors, and system administrators July 16, 2013
Test Contact Centre Solution July 26, 2013
Final decision July 30, 2013
Go-Live July 31, 2013